Fiona Stanley Hospital is now fully operational.

Our hospital opened progressively from October 2014 in a four-phased sequence that prioritised patient safety and care. Phase 4  was completed on 16 February 2015, ahead of the scheduled date 23 March 2015.

Phased opening

Phase 1

State rehabilitation service

Pathology, pharmacy and medical imaging providing support as required

Some intensive care capability

4 October 2014

Phase 2

 2A

General medicine (one 24-bed ward)

General surgical (one 24-bed ward)

Orthopaedics

Anaesthetics

Hyperbaric medicine

17 November 2014

 2B

Obstetrics

Gynaecology

Neonates

2 December 2014

Phase 3

Emergency department (7am)

Majority of all other specialities

Outpatient services

Burns

3 February 2015

Phase 4

Heart and lung transplant services

16 February 2015